Cibubur Line

The Jabodebek LRT Cibubur Line (Indonesian: LRT Jabodebek Lin Cibubur) is one of the two light rail line of the Jabodebek LRT which will connect Dukuh Atas to Harjamukti station, which is about 25.94 km in length. The line adopts elevated construction and stops at twelve stations.

Cibubur Line
Trial run at Harjamukti Station
Overview
Other name(s)Service line 1 of LRT Jabodebek (working name)
Native nameLin Cibubur
StatusUnder construction
OwnerMinistry of Transportation
LocaleJakarta, West Java
Termini
Stations12
Service
TypeLight rail transit
SystemJabodebek LRT
Services1
Operator(s)Kereta Api Indonesia
Depot(s)Harjamukti (pit stop)
History
Planned openingJune 2023 (expected)[1][2][3]
Completed2022 [3]
Technical
Line length25.94 km (16.12 mi)
Number of tracks2
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC Third rail system
Route map

Dukuh Atas
Setiabudi
Rasuna Said
Kuningan
Pancoran
Cikoko
Ciliwung
Cawang
to Jatimulya
TMII
Jagorawi Toll Road│JORR
Kampung Rambutan
Ciracas
Harjamukti
planned extension to Baranangsiang

Its Pancoran–Harjamukti section runs along the Jakarta Inner Ring Road and Jagorawi Toll Road. The planned next phase would extend the line to Bogor.[4]

History

The Greater Jakarta LRT elevated route is built parallel with the Jagorawi Toll Road.

Just like other public transportation systems in Jabodetabek, the Greater Jakarta LRT system was built to break down congestion. The construction of the Cawang-Cibubur LRT Line and other lines in the first phase of the Greater Jakarta LRT construction began with the groundbreaking on 9 September 2015 by President Joko Widodo. The groundbreaking ceremony was carried out near the planned TMII Station which is included in this LRT route.[5]

Initially, the construction of phase 1 was targeted to be completed before the 2018 Asian Games. However, until the Asian Games were held, the overall development for phase 1 itself was still 45%. Even so, at that time several lines in the Cawang–Cibubur service route had already begun to be fitted with rails.[6]

In March 2019, the entire track line has been connected. All elevated construction work has been completed and continued with signaling work and station construction. Therefore, this line is estimated to be ready for the trial run of the LRT series considering that the other lines have not yet completed their track construction.[7][8]

On October 11, 2019, the first series of Jabodebek LRT arrived in Jakarta. The shipment was carried out by land directly from the PT INKA Madiun Factory. For the time being, the LRT series has been parked near Harjamukti Station. This wad done considering that the construction of the LRT depot in Jatimulya has not yet been completed.[9][10]

In October 2020, the Greater Jakarta LRT fleet began trials. This trial was carried out on the Cawang–Cibubur service route with the TMII Station–Harjamukti Station route. This trial was conducted to check signaling readiness and the path to be traversed.[11][12]

Network

Route

The Cibubur Line has a track length of 25.94 kilometers.[13] Most of the trajectory of this route is using an elevated structure. From Dukuh Atas station to Cawang station, this line shares the route with Lin Bekasi, goes along Jalan Rasuna Said then turns to cross to the south side of the Cawang-Pluit Toll Road. After Cawang station, the two lines split and this line follows the Jagorawi Toll Road alignment.[14] From Cawang Station to TMII Station, the route changes from the west side to the east side of the toll road. Between the Cawang – TMII plots, there is a path made above ground level because it is close to the approach zone of Halim Perdanakusuma Airport. After TMII Station, the route moves back to the west side of the toll road to Harjamukti Station.[15]

List of stations

Station number Station Transfer/Notes Location
Phase 1: Cibubur–Dukuh Atas (under operational trial)
CB01 BK01 Dukuh Atas Terminus station.

Dukuh Atas BNI

Sudirman

BNI City

(4C) (13C) K1-9 Dukuh Atas 1

(L4) K4-17 Dukuh Atas 2

South Jakarta Jakarta
CB02 BK02 Setiabudi (4H) (9M) (13E) K6-17 Setiabudi Utara AINI
CB03 BK03 Rasuna Said (4H) (9M) (13E) K6-14 GOR Sumantri
CB04 BK04 Kuningan (4H) (9M) (13E) K6-13 Departemen Kesehatan
CB05 BK05 Pancoran (4K) (9M) (13C) (13F) K9-10 Pancoran Barat
CB06 BK06 Cikoko Cawang

(4K) (9M) (13F) K9-7 Cikoko Stasiun Cawang

CB07 BK07 Ciliwung (4K) (9M) (13F) K9-6 Cawang Ciliwung East Jakarta
CB08 BK08 Cawang

Planned interchange station to

(4K) (L7) (9M) K7-10 Cawang BNN

CB09 Taman Mini (9M) K9-2 Garuda Taman Mini

Access to Taman Mini Indonesia Indah.

CB10 Kampung Rambutan (7F) (7M) (L7) (9K) (10D) K7-1 Kampung Rambutan

Kampung Rambutan Bus Terminal.

CB11 Ciracas
CB12 Harjamukti Terminal station (phase 1). Depok West Java
Phase 2: Cibubur–Bogor (under feasibility study)
Phase (?): Dukuh Atas–Senayan (under feasibility study)
CB01 BK01 Palmerah Palmerah Central Jakarta Jakarta
CB02 GBK
CB03 Senayan Senayan

(6V) (10H) Bundaran Senayan

Future development

In the phase 2 construction plan, the LRT line is planned to be extended to Bogor along with the Dukuh Atas-Senayan service line.[16][17] The Cibubur-Bogor route is planned to be built on the ground, not elevated like the Cawang-Cibubur route. This above-ground building model is considered to save construction costs by up to 50%.[18] Until now, the Cibubur-Bogor route is still in the design planning process.[19][20]

Incidents

On October 25, 2021, 2 LRT train series had an accident while undergoing trials on this line, parallel to the Jakarta-Bogor-Ciawi Toll Road.[21][22]

References

  1. Yanwardhana, Emir. "Molor Berkali-Kali, LRT Jabodebek Baru Bisa Operasi 2023". CNBC Indonesia (in Indonesian). Retrieved 2022-10-31.
  2. Afriyadi, Achmad Dwi. "Sabar Ya Warga! LRT Jabodebek Baru Operasi Juni 2023". detikfinance (in Indonesian). Retrieved 2022-10-31.
  3. "Proyek LRT Jabodebek Molor ke 2022" (in Indonesian). 5 June 2020. Retrieved 27 June 2020.
  4. Dewi Rina Cahyani (ed.). "Proyek LRT Cibubur - Bogor Ditargetkan Rampung 3 Tahun" (in Indonesian). Retrieved 11 November 2019.
  5. "LRT JABODETABEK: Jokowi 'Groundbreaking' Hari Ini". Bisnis.com (in Indonesian). 2015-09-09. Retrieved 2023-01-04.
  6. Media, Kompas Cyber (2018-08-21). "Konstruksi Sipil LRT Jabodebek Rampung Akhir 2018". KOMPAS.com (in Indonesian). Retrieved 2023-01-04.
  7. "Lintas Cawang-Cibubur Tersambung, Progres LRT Capai 60 Persen". CNN Indonesia (in Indonesian). Retrieved 2023-01-04.
  8. Alhikam, Herdi Alif. "Fakta Jalur LRT Cibubur-Cawang Sudah Tersambung". detikfinance (in Indonesian). Retrieved 2023-01-04.
  9. Lidyana, Vadhia. "Penampakan LRT Jabodebek yang Tiba di Jakarta". detikfinance (in Indonesian). Retrieved 2023-01-04.
  10. "Fakta-Fakta Terbaru LRT Jabodebek, Termasuk Tarif Rp12.000 Semua Halaman". merdeka.com. 2019-10-15. Retrieved 2023-01-04.
  11. Anwar, Muhammad Choirul. "Uji Coba LRT Cibubur: Mulai Mondar-Mandir, Kapan Operasi?". CNBC Indonesia (in Indonesian). Retrieved 2023-01-04.
  12. Okezone (2020-10-22). "Jam 2 Siang, Uji Coba LRT Jabodebek 4 kali Bolak-balik : Okezone Economy". economy.okezone.com/ (in Indonesian). Retrieved 2023-01-04.
  13. Media, Kompas Cyber (2019-07-27). "Panduan Lengkap LRT Jabodebek, Rute dan Stasiun". KOMPAS.com (in Indonesian). Retrieved 2023-01-04.
  14. "Konstruksi Jalur LRT Berada di Sisi Kanan Tol Jagorawi". TEMPO.CO (in Indonesian). 21 October 2015. Retrieved 2023-01-04.
  15. Aditiasari, Dana. "Cibubur-Cawang Terhubung LRT, Ini Jalurnya". detikfinance (in Indonesian). Retrieved 2023-01-04.
  16. Aliya, Angga. "Ini Dia Rute-rute LRT Jokowi yang akan Dibangun Adhi Karya". detikfinance (in Indonesian). Retrieved 2023-01-04.
  17. "Ini Rute LRT dari Bekasi, Bogor, Depok dan Jakarta". suara.com (in Indonesian). 2015-09-09. Retrieved 2023-01-04.
  18. Pramisti, Nurul Qomariyah. "LRT Jabodebek Tahap 2 Arah Bogor Dibangun di Darat, Biaya Turun 50%". tirto.id (in Indonesian). Retrieved 2023-01-04.
  19. "Pembangunan Lintas Rel Terpadu Tahap II Rampung dalam 3 Tahun". Bisnis.com (in Indonesian). 2019-11-11. Retrieved 2023-01-04.
  20. Siregar, Efrem. "Kabar Gembira! LRT Cibubur-Sentul-Bogor Siap Dieksekusi". CNBC Indonesia (in Indonesian). Retrieved 2023-01-04.
  21. "BREAKING NEWS: LRT Jabodetabek Tabrakan di Atas Ruas Tol Jagorawi Jakarta Timur". Tribunnews.com (in Indonesian). Retrieved 2023-01-04.
  22. Liputan6.com (2021-10-25). "LRT Jabodebek Tabrakan di Jalur Layang Cibubur, Adhi Karya Kirim Tim ke Lapangan". liputan6.com (in Indonesian). Retrieved 2023-01-04.